3.10.1 Frame subject to priority determination

Priority determination operation change is a function that makes a frame addressed to the Switch that is not subject to priority determination a target for priority determination. By default, only frames forwarded by the Switch are subject to priority determination. The table below describes switch configurations, the setting for changing which frames are subject to priority determination, and the corresponding frames subject to priority determination.

Table 3-11: Frames subject to device configuration and priority determination

Switch configuration

Setting for changing which frames are subject to priority determination

Frame type

Frames sent to the Switch

Frames forwarded by the Switch

All models

(in standalone mode)

Not set

NG

OK

Set

OK

OK

All models

(in stack mode)

Not set

OK

OK

Set

OK

OK

Legend: OK: Becomes subject to priority determination, NG: Does not become subject to priority determination